Question
A client for a construction project gave their contractor site possession 3 months after the date for possession stated in the contract. During the 3-month
A client for a construction project gave their contractor site possession 3 months after
the date for possession stated in the contract. During the 3-month 'waiting period',
the contractor sent multiples notices to the contract administrator to request to
suspend the work. The contract administrator received the contractor's requests but
did not issue any instructions to suspend the work.
Eventually, the contractor proceeded with their works but struggled to catch up with
the contract's deadline. The project did not complete on time despite the contractor's
best efforts. The project is now delayed by 4 weeks, and the client charged the
contractor liquidated damages (LD) for each delayed day. The contractor contested
the LD charges and asserted that the delay was wholly caused by the client's fault.
The contractor argued that the contract time has become at large and the contractor
was no longer obliged to complete by a fixed completion date and need only
complete the work within reasonable time without imposing LD.
The client contended that the contractor had waived their rights to avoid LD charges
by failing to apply for an extension of time (EOT) following the delayed site
possession. The client emphasised, "No EOT application means no EOT approval,
so LD should be chargeable'".
The project uses NZS3910:2013 as the contract.
discuss on Late site possession related to the case above (position under common law
and position under contract)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started