A clothing manufacturer is upgrading their production machinery. The company operates three eight - hour shifts per day; they would like to minimize down -

A clothing manufacturer is upgrading their production machinery. The company operates three eight-hour shifts per day; they would like to minimize down-time during the upgrade.
\table[[,Activity,Precedes,\table[[Duration],[(hours)]]],[A,Order and receive new machines P and Q,B,480],[B,Stop production,C, G, H,2],[C,Remove old machine Q,D,2],[D,Prepare machine base for Q,E,8],[E,Install new machine Q,F,2],[F,Test and commission machine Q,L,3],[G,Remove old machine P,H,1],[H,Prepare new electrical feed for P,J, L,5],[J,Install new machine P,K,2],[K,Commission and test machine P,L,12],[L,Start production,,1]]
a. How much production down-time is needed for this project?
b. Using your knowledge of production systems, revise the project precedence to minimize the production down-time. Justify your answer.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Small Business Management Entrepreneurship and Beyond

Authors: Timothy s. Hatten

5th edition

538453141, 978-0538453141

More Books

Students also viewed these General Management questions