Question
1 Approved Answer
A company began work in 2020 on a contract for $7,800. Other data are as follows: 2020 2021 Costs incurred to date $3,000 $5,600 Estimated
A company began work in 2020 on a contract for $7,800. Other data are as follows:
2020 2021
Costs incurred to date $3,000 $5,600
Estimated costs to complete 2,000
Billings to date 4,400 7,800
Collections to date 2,000 4,800
If the company uses the percentage-of-completion method, for the journal entry that records construction revenue, construction expense, and gross profit for 2020, how much will be recorded for Construction in Process?