A company buys an item from a supplier at a unit price of SEK 200. Demand is estimated at 250 units per week. The refill
A company buys an item from a supplier at a unit price of SEK 200. Demand is estimated at 250 units per week. The refill special cost is SEK 350 per order and the company works with an annual stock interest rate of 20%. The lead time is 2 weeks. Assume that it takes 52 weeks in a year.
Calculate the order point for the product. Round to the nearest integer