A Company entered into a construction agreement in 2019 that called for a contract price of P9,600,000. At the beginning of 2020, a change in

A Company entered into a construction agreement in 2019 that called for a contract price of P9,600,000. At the beginning of 2020, a change in order increase in the initial contract price by P480,000. In relation to the project, the following data were obtained:

Description 2019 2020

Costs incurred to date P4,920,000 P8,640,000

Estimated costs to complete 4,920,000 2,160,000

Billings made to date 5,280,000 8,700,000

Collections made to date 4,920,000 8,700,000

Compute the amount of construction in progress (net) for the year 2020.

Group of answer choices

A. POC method - P780,000 liabilities ; Cost recovery method - P780,000 Liabilities

B. POC method - P60,000 liabilities ; Cost recovery method - P60,000 Liabilities

C. POC method - P780,000 Assets ; Cost recovery method - P780,000 Assets

D. POC method - P630,000 liabilities ; Cost recovery method - P630,000 Liabilities

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accountability Ethics And Sustainability Of Organizations

Authors: Sandro Brunelli, Emiliano Di Carlo

3rd Edition

3030311929, 9783030311926

More Books

Students also viewed these Accounting questions