A company expected its annual overhead costs to be $787500 and machine hours to equal 105000 hours. Actual overhead was $750000, and actual machine hours
A company expected its annual overhead costs to be $787500 and machine hours to equal 105000 hours. Actual overhead was $750000, and actual machine hours totalled 96000 hours. How much overhead was over or underapplied?
| $30000 underapplied |
| $67500 underapplied |
| $70000 over-applied |
| $37200 underapplied |