A company has a project to complete. To complete the project, the following activities should be done. Draw the Project Diagram/Network (15 pts) of this
A company has a project to complete. To complete the project, the following activities should be done. Draw the Project Diagram/Network (15 pts) of this project and develop a Linear Program (20 pts) for computing a critical path (NO NEED TO SOLVE IT). Activity Predecessors Duration (months) 4 3 A B C D - 8 2 A 6 E B, D 7 F E, C 1 G E H F, G 4