A company has collected the following data regarding an order: Move time 0.8 days Inspection time 0.3 days Queue time 1.2 days Process time 6.5
A company has collected the following data regarding an order:
Move time 0.8 days
Inspection time 0.3 days
Queue time 1.2 days
Process time 6.5 days
Wait time 8.2 days
a) Calculate throughput (manufacturing cycle) time
b) Calculate manufacturing cycle efficiecy (MCE)
c) Calculate delivery cycle time