A company has consistently used the overtime/percentage of completion method. On January 2019, the company began work on a P6,000,000 construction contract. At the inception

A company has consistently used the overtime/percentage of completion method. On January 2019, the company began work on a P6,000,000 construction contract. At the inception date, the estimated costs of construction was P4,500,000. The following data relate to the progress of the contract:

Income recognized at 12/31/19 -- P600,000 Costs incurred 1/10/19 through 12/31/20 -- 3,600,000 Estimated cost to complete at 12/31/20 -- 1,200,000

How much income should the company recognize for the year ended December 31, 2020?

Group of answer choices

A. P900,000

B. P535,000

C. P600,000

D. P300,000

Show solution.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accountability Ethics And Sustainability Of Organizations

Authors: Sandro Brunelli, Emiliano Di Carlo

3rd Edition

3030311929, 9783030311926

More Books

Students also viewed these Accounting questions

Question

Over what timescale should the project be undertaken?

Answered: 1 week ago