Question
A company has consistently used the overtime/percentage of completion method. On January 2019, the company began work on a P6,000,000 construction contract. At the inception
A company has consistently used the overtime/percentage of completion method. On January 2019, the company began work on a P6,000,000 construction contract. At the inception date, the estimated costs of construction was P4,500,000. The following data relate to the progress of the contract:
Income recognized at 12/31/19 -- P600,000 Costs incurred 1/10/19 through 12/31/20 -- 3,600,000 Estimated cost to complete at 12/31/20 -- 1,200,000
How much income should the company recognize for the year ended December 31, 2020?
Group of answer choices
A. P900,000
B. P535,000
C. P600,000
D. P300,000
Show solution.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started