Question

1 Approved Answer

A company i s working o n a project with a budget o f $ 1 0 0 0 . The planned value a s

A company is working on a project with a budget of $1000. The planned value asof today is $400. The project is30% complete and 60%of the budget has been spent.
a.) According to the budget, the cost variance is:
b.)If the company continues to spend at the same rate, the project cost will be:
c.) What is the estimate to complete (ATC)?
They answers are a.) $60 b.)$800 c.) $560
I know the answers but can someone help me understand the work required to achieve these answers.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

differentiate between challenge and hindrance demands;

Answered: 1 week ago