Question

1 Approved Answer

A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to

A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of
400
units per day. The tasks necessary to produce this product are detailed in the table below.
Task Predecessor Time
(
seconds
)
A
-
50
B A
36
C
-
26
D
-
22
E B
,
D
70
F C
,
E
30
a
.
What is the cycle time?
[
Select
]
b
.
What is the theoretical minimum number of stations?
[
Select
]
c
.
Were you able to assigned the tasks based on the theoretical number of stations?
[
Select
]
d
.
Based on the longest operating time, what is the station assignment?
[
Select
]
e
.
What is the efficiency of the assembly line?
[
Select
]
f
.
How much idle time is there?
[
Select

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Supply Chain Network Design Applying Optimization and Analytics to the Global Supply Chain

Authors: Michael Watson, Sara Lewis, Peter Cacioppi, Jay Jayaraman

1st edition

133017370, 978-0133017373

More Books

Students also viewed these General Management questions