Question
1 Approved Answer
A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to
A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of
units per day. The tasks necessary to produce this product are detailed in the table below.
Task Predecessor Time
seconds
A
B A
C
D
E B
D
F C
E
a
What is the cycle time?
Select
b
What is the theoretical minimum number of stations?
Select
c
Were you able to assigned the tasks based on the theoretical number of stations?
Select
d
Based on the longest operating time, what is the station assignment?
Select
e
What is the efficiency of the assembly line?
Select
f
How much idle time is there?
Select
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started