Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to
A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of units per day. The tasks necessary to produce this product are detailed in the table below.
Task Predecessor Time seconds
A
B A
C
D
E B D
F C E
a What is the cycle time?
seconds
b What is the theoretical minimum number of stations?
Select
c Were you able to assigned the tasks based on the theoretical number of stations?
Select
d Based on the longest operating time, what is the station assignment?
Select
e What is the efficiency of the assembly line?
Select
f How much idle time is there?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started