A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to
A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of units per day. The tasks necessary to produce this product are:
Task Timesecs Immediate
Predecessor
u none
v u
w u
x w
y x
z vy
Without regard to demand, what is the minimum possible cycle time in seconds for this situation?