A company manufactures boxes of staples. Staple boxes contain ten cartridges to a box. The lead time to package a box is two weeks. Using

A company manufactures boxes of staples. Staple boxes contain ten cartridges to a box. The lead time to package a box is two weeks.
Using this MRP Grid, what are the net requirements for week 4?
Week Number 1 2 3 4
Box Gross Requirement 1500 1000 500 2000
Beginning Inventory 0 Scheduled Receipt 2000 500
LT 2 Projected On Hand 2000 1000 0
Order Policy Fixed 500 Net Requirement 0 0 500
SS 0 Planned order Receipt 500
Planned Order Release 500
Week Number 1 2 3 4

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations management

Authors: Jay Heizer, Barry Render

10th edition

978-0136119418, 136119417, 978-0132163927

More Books

Students also viewed these General Management questions

Question

What is the mode?

Answered: 1 week ago

Question

What can be done to change the health habits of populations?

Answered: 1 week ago