Question
A company manufactures small assembles to order and has the following budgeted Overheads for the year base on normal activity levels. Departments Building Overheads Overhead
A company manufactures small assembles to order and has the following budgeted
Overheads for the year base on normal activity levels.
Departments Building Overheads Overhead absorption base
Blanking 18000 1500 labour hours
Machining 43000 2500 Machine hours
Welding 20000 1800 labour hours
Assembling 15000 1000 labour hours
Selling and administration overheads are 20% of factory cost.
An order for 250 assemblies type x 128 made as batch 5931 incurred the following cost.
Materials 3107
Labour 128 hours blanking shop at 5.25 per hour.
452 hours machining shop at 5.50 per hour.
90 hours welding shop at 5.25 per hour.
175 hours assembling shop at 4.80 per hour.
525 was paid for the hire of special x-ray equipment for testing welds.
The time booking for the machine shop is a 643-machine hour.
Required: Calculate the total cost of the batch, the unit cost and the profit per assembly if the selling price was 150 per assembly
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started