A company provided the following direct materials cost information. Compute the direct materials price variance. Standard costs assigned: Direct materials standard cost (413,000 units @
A company provided the following direct materials cost information. Compute the direct materials price variance.
Standard costs assigned:
Direct materials standard cost (413,000 units @ $3.00/unit) $1,239,000
Actual costs:
Direct Materials costs incurred (412,550 units @ $3.20/unit) $1,320,160
- $82,600 Favorable.
- $82,510 Favorable.
- $82,510 Unfavorable.
- $1,239,000 Favorable.
- $1,239,000 Unfavorable.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started