A company provided the following direct materials cost information. Compute the direct materials price variance. Standard costs assigned: Direct materials standard cost (419,000 units @
A company provided the following direct materials cost information. Compute the direct materials price variance.
Standard costs assigned: | |||
Direct materials standard cost (419,000 units @ $3.00/unit) | $ | 1,257,000 | |
Actual costs: | |||
Direct Materials costs incurred (416,000 units @ $3.20/unit) | $ | 1,331,200 | |
Multiple Choice
-
$1,257,000 Favorable.
-
$1,257,000 Unfavorable.
-
$83,200 Unfavorable.
-
$83,200 Favorable.
-
$83,800 Favorable.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started