A company wants to estimate the probability of a project being completed within a specific time frame. Which statistical method involves simulating the project's schedule
A company wants to estimate the probability of a project being completed within a specific time frame. Which statistical method involves simulating the project's schedule multiple times to assess the likelihood of meeting the deadline? Group of answer choices Regression analysis Monte Carlo simulation Control chart Pareto analysis