Question

1 Approved Answer

A company's construction time follows a normal distribution. The mean time to construct a building is 82 days and the standard deviation is 15 days.

image text in transcribed
A company's construction time follows a normal distribution. The mean time to construct a building is 82 days and the standard deviation is 15 days. The construction team will receive a penalty if completion of the job exceeds 100 days. What is the probability that they will receive a penalty? O 0.8974 0.1026 O 0.1151 O 0.8849 O 0.1915

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

WebAssign For Trigonometry

Authors: James Stewart

2nd Edition

1337772313, 9781337772310

More Books

Students also viewed these Mathematics questions

Question

3. Tactical/strategic information.

Answered: 1 week ago

Question

3. To retrieve information from memory.

Answered: 1 week ago

Question

2. Value-oriented information and

Answered: 1 week ago