A component used in a manufacturing facility is ordered from an outside supplier. The time - phased net requirements for the component over the next

A component used in a manufacturing facility is ordered from an outside supplier. The
time-phased net requirements for the component over the next 7 weeks are 5,25,17,15,
25,13, and 27. Assume a holding cost of $1.5 per week and a setup cost of $42.
1) Determine the order policy for this item over the next 7 weeks based on Silver-Meal
heuristic.
2) Assume there is a capacity constraint to the lot sizing
a. Suppose that the maximum order size is 15 per week. Does there exist a feasible
solution?
b. Suppose that the maximum order size is 25 per week. Use lot-shifting technique to
obtain a feasible solution (without using holding and setup cost).
c. Suppose that the maximum order size is 25 per week. Improve the solution
obtained in Part (b)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Process

Authors: Lee Long

4th Edition

978-0201822939,0201822938

More Books

Students also viewed these General Management questions