Question
A concrete worker works 10 hr/day, 6 days/week; Base wage of $26.00/hr is paid for all straight-time work, 8 hr/day, 5 days/week; The overtime rate
A concrete worker works 10 hr/day, 6 days/week;
Base wage of $26.00/hr is paid for all straight-time work, 8 hr/day, 5 days/week;
The overtime rate is 1.5 times for all hours over 8 hr/day on Monday through Friday and 2 times for all hours worked on Saturdays;
The social security tax is 7.65% of actual wages;
Unemployment tax is 2% of actual wages;
Workers compensation insurance is $5.50/$100 of base wage;
Public liability and property damage insurance rate is $2.25/$100 of base wage;
Fringe benefits are $2.50/hr;
Determine the average hourly and weekly cost of the crew and the labor $/SF of concrete
Suppose there are 5 concrete workers in a crew and the crew can place and finish 2,400
SF of flat slab concrete per day. Determine the labor cost per SF of concrete in place.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started