a. Construct the network diagram. b. Find each activitys ES, EF, LS, and LF. c. Identify all
Fantastic news! We've Found the answer you've been seeking!
Question:
a. Construct the network diagram.
b. Find each activitys ES, EF, LS, and LF.
c. Identify all paths. Which path is the critical path?
d. How long will it take to complete the project?
Transcribed image text : \begin{tabular}{|c|c|c|} \hline Activity & Duration & Predecessors \\ \hline a & 2 & None \\ \hline b & 3 & None \\ \hline c & 2 & a \\ \hline d & 4 & a, b \\ \hline e & 4 & c \\ \hline f & 3 & c \\ \hline g & 5 & d, e \\ \hline h & 2 & f, g \\ \hline \end{tabular}
Posted Date: