(a) Construct the network diagram of these activities. [7 marks] (b) Determine the critical path. [23 marks] Requirements for (b) 1. Earliest Start Time [10
(a) Construct the network diagram of these activities. [7 marks] (b) Determine the critical path. [23 marks] Requirements for (b) 1. Earliest Start Time [10 MARKS] ii. Latest Completion Time [10 MARKS] iii. Critical Path [3 MARKS] Immediate Predecessor Duration (months) 1 Table 1 Activity A B C D E F G H 4 2 2 3 3 2 1 - J B B AD AD B C.E F G.HU G.HU J KL MN K L M N P 3 2 3 6 5 2 4 7