Question
A construction company accepted a contract to build a bridge for $ 7,000,000. Construction activity began early in Year 1 and was concluded during Year
A construction company accepted a contract to build a bridge for $ 7,000,000. Construction activity began early in Year 1 and was concluded during Year 3. Information pertaining to the construction was as follows:
Costs As of Year-End Billings Collections Incurred Estimated Costs To During During Year DURING YEAR Complete Construction Year Year 1 $1,000,000 $3,000,000 $1,750,000 $1,500,000 2 2,000,000 2,000,000 2,450,000 2,000,000 3 3,000,000 -0- 2,800,000 3,500,000 Totals 6,000,000 7,000,000 7,000,000 The amount of REVENUE and GROSS PROFIT OR (LOSS) to be recognized under the Percentage of Completion method in Year 2 are:
Group of answer choices
Revenue recognized of $1,750,000 and Gross Profit recognized of $750,000.
Revenue recognized of $2,450,000 and Gross Profit recognized of $450,000.
Revenue recognized of $4,200,000 and Gross Profit recognized of $1,200,000.
Revenue recognized of $2,450,000 and Gross Profit recognized of $1,200,000.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started