Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A construction company accepted a contract to build a bridge for $ 7,000,000. Construction activity began early in Year 1 and was concluded during Year

A construction company accepted a contract to build a bridge for $ 7,000,000. Construction activity began early in Year 1 and was concluded during Year 3. Information pertaining to the construction was as follows:

Costs As of Year-End Billings Collections Incurred Estimated Costs To During During Year DURING YEAR Complete Construction Year Year 1 $1,000,000 $3,000,000 $1,750,000 $1,500,000 2 2,000,000 2,000,000 2,450,000 2,000,000 3 3,000,000 -0- 2,800,000 3,500,000 Totals 6,000,000 7,000,000 7,000,000 The amount of REVENUE and GROSS PROFIT OR (LOSS) to be recognized under the Percentage of Completion method in Year 2 are:

Group of answer choices

Revenue recognized of $1,750,000 and Gross Profit recognized of $750,000.

Revenue recognized of $2,450,000 and Gross Profit recognized of $450,000.

Revenue recognized of $4,200,000 and Gross Profit recognized of $1,200,000.

Revenue recognized of $2,450,000 and Gross Profit recognized of $1,200,000.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting A Managerial Emphasis

Authors: Charles T. Horngren, George Foster, Srikant M. Datar, Madhav T. Rajan, Chris M. Ittner

13th Edition

0131355589, 978-0131355583

More Books

Students also viewed these Accounting questions