A construction company enters into a contract to build a house for $200,000. The project is expected to take 10 months to complete. At the
A construction company enters into a contract to build a house for $200,000. The project is expected to take 10 months to complete. At the end of the first month, the company incurs $15,000 in costs related to the project. Calculate the percentage of completion and the revenue recognized for the first month using the percentage-of-completion method.