A construction company is bidding for a project and needs to estimate its costs accurately. The project requires 5,000 hours of labor. The company's total
A construction company is bidding for a project and needs to estimate its costs accurately. The project requires 5,000 hours of labor. The company's total fixed costs for overheads, equipment, and administrative expenses are $300,000, and its variable costs per labor hour are $50. If the company wants to make a 20% profit on the project, what should its bid price per labor hour be?