A construction company is building a new home for one of its customers; however, bad weather has delayed the finish of the project by two
A construction company is building a new home for one of its customers; however, bad weather has delayed the finish of the project by two weeks. After evaluating the schedule, the project manager determines that the plumbing and electrical work can be done simultaneously instead of separately, as originally planned. This is an example of