A construction company started business in January 2019 and is in the process of producing the budget for the year 2020. During the year 2019,
A construction company started business in January 2019 and is in the process of producing the budget for the year 2020. During the year 2019, the contractor won and started four contracts. The value, starting date, duration and profit are as follows:
Contract Month Duration (Months) Value (£M) Profit (£M) 1
Started 2019
March 20 15 1.5 2
April 12 10 1.0 3
May 9 9 0.9 4
December 20 12 1.2
a) Calculate the turnover for the year 2020 if no more contracts are won during that year (assume a uniform rate of value build up on any contract). (8 marks)
b) Calculate the total value and number of contracts to be won during the year 2020 for the contractor to be able to achieve the following profit targets:
i. Pay the second annual instalment of a £10 million loan taken at the beginning of the 2019 to be settled in equal annual instalments within 10 years (assuming 10% compound interest rate).
ii. Pay Dividends of £400,000
iii. Retain profit of £1,000,000
You may assume that the average duration of projects to be started in 2020 is 15 months and an average contract is worth £6 million.
Step by Step Solution
3.34 Rating (163 Votes )
There are 3 Steps involved in it
Step: 1
Contand Morth Decker Valur Daft Cuteal fol 4 Hound...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started