Question

1 Approved Answer

A construction contractor has undertaken a job with 7 major tasks. Some of the tasks can begin at any time, but others have predecessors that

A construction contractor has undertaken a job with 7 major tasks. Some of the tasks can begin at any time, but others have predecessors that must be completed first. The following table shows those predecessor task numbers, together with the minimum and maximum time (in days) allowed for each task, and the total cost that would be associated with accomplishing each task in its minimum and maximum times. Here, more time spent reduces cost, because otherwise the contractor has to pay for more expensive pre-finished products and/or pay for an assistant. Provided precedence constraints are met, the contractor can work on multiple projects in parallel (eg. while he waits for paint to dry at one house he can install cabinets in another).

The contractor seeks a way to complete work in 40 days, at least total cost, assuming that the cost of each task is linearly interpolated for times between the minimum and maximum.

Formulate a linear optimization model for this problem. Clearly define in words what your decision variables represent.

image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Marketing

Authors: David Bowie, Francis Buttle

3rd Edition

1317403495, 9781317403494

More Books

Students also viewed these General Management questions