A construction project at Month 4 has a scheduled cost of $56,000, actual costs of $60,000, and an earned value of $50,000. The project cost
A construction project at Month 4 has a scheduled cost of $56,000, actual costs of $60,000, and an earned value of $50,000. The project cost variance is