Question

1 Approved Answer

A construction project consists of the following activities Immediate predecessor (s) Optimistic time I Activity A B C D E F G H

 

A construction project consists of the following activities Immediate predecessor (s) Optimistic time " I Activity A B C D E F G H I J K L M N O P EMBE A A B B.C. C F E D.G H LJ IJ K L M . HUNGA 4 4 5 53 2 5 1 5 1 10 1 2 4 3 2 1 Most probable 9 5 11 5 4 8 2 7 4 12 4 7 6 5 6 1 Pessimistic time 12 8 13 7 7 11 3 10 7 14 6 12 22 12 9 12 1 Develop a critical path diagram. What is the critical path, how long does it take to complete the project? Find ES, LS, EF, LF and the slack time for each activity. If you want a 0.96 probability of completing the project on time, how far ahead of the scheduled completion date should you begin working on the project

Step by Step Solution

3.50 Rating (163 Votes )

There are 3 Steps involved in it

Step: 1

Since the activities are probabilistic in nature apply Project Evaluation and Review Technique PERT The PERT considers that the activity duration foll... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Digital Logic With Verilog Design

Authors: Stephen Brown, Zvonko Vranesic

3rd Edition

978-0073380544, 0073380547

More Books

Students also viewed these Accounting questions