A construction site has 84 tons of waste it needs to dispose of. The construction workers are only able to remove 3 tons of waste

image text in transcribed
A construction site has 84 tons of waste it needs to dispose of. The construction workers are only able to remove 3 tons of waste per day. 1. Find an equation that expresses the amount of waste at the construction site in terms of the number of days the construction workers have been removing the waste y= 2. What is the y-intercept? Interpret it. y-intercept (z, y) = ( If the construction workers have spend days removing the waste, there will be tons of waste remain ng at the construction site. 3. What is the slope? Interpret it. Slope The line has atri) Seed in an g from left to right OF the construction workers work more days. there will be more waste remaining at the construction site Off the construction workers work less days re waste remain the construction she. Off the construction workers work s waste remaining at the construction sites Off the construction workers work less days, the waste remaining at the construction site 4. If the construction workers work B days how much wa remain at the construction site

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Engineering Mathematics

Authors: ERWIN KREYSZIG

9th Edition

0471488852, 978-0471488859

More Books

Students also viewed these Mathematics questions