Question
A consulting firm is planning a reengineering project for a client. The following activities and time estimates have been identified. Activity Time, Days Immediate Predecessor
A consulting firm is planning a reengineering project for a client. The following activities and time estimates have been identified.
Activity | Time, Days | Immediate Predecessor |
---|---|---|
A | 1 | / |
B | 2 | / |
C | 2 | / |
D | 2 | A, B |
E | 4 | A, C |
F | 1 | C |
G | 4 | D |
H | 8 | G, E, F |
a.) Draw a project network diagram.
b.) Calculate the scheduling times and total slack for each activity. (PLEASE SHOW EXCEL FORMULAS, DON'T JUST PUT THE ANSWER!)
c.) List the critical path activities for the project duration.
d.) Assuming that one worker is required for each activity, prepare a resource leveled schedule. What is the maximum number of workers required to finished the project on time? (PLEASE SHOW CALCULATIONS!)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started