A consulting firm is planning a reengineering project for a client. The following activities and time estimates have been identified. Activity Time, Days Immediate Predecessor

A consulting firm is planning a reengineering project for a client. The following activities and time estimates have been identified.

Activity Time, Days Immediate Predecessor
A 1 /
B 2 /
C 2 /
D 2 A, B
E 4 A, C
F 1 C
G 4 D
H 8 G, E, F

a.) Draw a project network diagram.

b.) Calculate the scheduling times and total slack for each activity. (PLEASE SHOW EXCEL FORMULAS, DON'T JUST PUT THE ANSWER!)

c.) List the critical path activities for the project duration.

d.) Assuming that one worker is required for each activity, prepare a resource leveled schedule. What is the maximum number of workers required to finished the project on time? (PLEASE SHOW CALCULATIONS!)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Warren R. Plunkett, Gemmy S. Allen

10th edition

1111221340, 978-1111221348

More Books

Students also viewed these General Management questions