A contractor agreed to build 30 model houses in 90 days at a price of RM 800 per unit. 20 days later, the contractor has

A contractor agreed to build 30 model houses in 90 days at a price of RM 800 per unit. 20 days later, the contractor has finished 8 model houses with an actual total cost (that includes his overhead and profit) of RM 6800. What is the status of the projects?

Calculate: i) BCWS ii) BCWP iii) ACWP iv) CV v) SV

Assume that the work is sequential and not parallel (i.e., the contractor works on one unit till it is finished then starts the next unit and so on)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Analysis And Decision Making

Authors: David E. Vance

1st Edition

0071406654, 9780071406659

More Books

Students also viewed these Accounting questions

Question

What is an unbounded solution?

Answered: 1 week ago

Question

Solve for t using natural logarithms. 10 = 2 t

Answered: 1 week ago

Question

In your opinion, is mental illness currently overdiagnosed?

Answered: 1 week ago