A contractor decided to use the techniques of project management to plan a job. He knew all the different activities of the job, the order

A contractor decided to use the techniques of project management to plan a
job. He knew all the different activities of the job, the order of precedence
and their average durations which are shown in the table below.
Required:
a) Draw a network diagram representing the sequence of activities and the
dependence between them.
b) Determine how long it will take to complete the job by conducting the
forward pass.
c) By conducting the backward pass, identify the critical path and the non-
critical path(s), showing all the duration of the paths.
Note:
The work for this task should be produced using Word drawing facilities OR
Excel (then copy diagram to Word). The forward and backward passes should
be clearly shown on the diagram. Each activity should be described using the
notation shown in class as follows:
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Stage Management

Authors: Lawrence Stern, Jill Gold

11th Edition

9781138124462

More Books

Students also viewed these General Management questions

Question

Understand the reasons for engaging consultants

Answered: 1 week ago