Question

1 Approved Answer

A contractor enters into a revenue contract to construct customized equipment for a customer. The contract price is $180,000 plus a $90,000 bonus if the

A contractor enters into a revenue contract to construct customized equipment for a customer. The contract price is $180,000 plus a $90,000 bonus if the customized equipment is completed by a specified date. The contract is expected to take three years to complete. The contractor has extensive experience in building customized equipment. The award fee is paid only if the customized equipment is completed by the agreed upon date. Otherwise, the contractor receives no bonus. The contractor estimates that it is 80% likely that the contract will be completed successfully and in advance of the target date.

its not 252,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Budgeting And Financial Management For Nonprofit Organizations Using Money To Drive Mission Success

Authors: Lynne A. Weikart, Greg G. Chen, Edward M. Sermier

1st Edition

1608716937, 978-1608716937

More Books

Students also viewed these Accounting questions

Question

Why is the sample range a poor measure of spread?

Answered: 1 week ago

Question

discuss different sources of numerical data;

Answered: 1 week ago

Question

design and evaluate an effective survey instrument;

Answered: 1 week ago

Question

administer a survey to an appropriate sample of respondents;

Answered: 1 week ago