A contractor has agreed to build 30 dog houses in 90 days at a price of $800 per unit. Twenty days later, the contractor has
A contractor has agreed to build 30 dog houses in 90 days at a price of $800 per unit. Twenty days later, the contractor has finished 8 dog houses with an actual total cost (that includes overhead and profit) of $6,800. What is the status of the project? Fill out the table below also show necessary calculations done to fill out the table. What is project status in terms of cost and schedule