Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A contractor has developed the tasks, durations, and predecessor relationships in the following table for part of a new building. The Beta distribution is assumed

A contractor has developed the tasks, durations, and predecessor relationships in the following table for part of a new building. The Beta distribution is assumed for all activity times.
Task Immediate Predecessor(s) Time Estimates (In Weeks)
Optimistic Most Likely Pessimistic
A None 5619
B A 567
C A 345
D B 135
E B 3417
F C 246
G D 345
H E, F 234
7. Draw the precedence network for the project. You may use the shape tools in Word or PowerPoint, or the drawing application of your choice, and insert (copy & paste) the diagram into the Word file. What are the ES/EF (earliest start/finish) and the LS/LF (latest start/finish) for each task based on the expected task times? Write these times on the network diagram. Hint: It may be helpful to create dummy start and/or end tasks with task times of 0 to tie the ends of the network together. (10 pts)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Management Information Systems

Authors: Ken Laudon, Kenneth C Laudon

10th Edition

0133033090, 9780133033090

More Books

Students also viewed these General Management questions