A contractor must choose between buying or renting a crane for the duration of a 4 year construction project. The contractor uses an MARR of

A contractor must choose between buying or renting a crane for the duration of a 4 year construction project. The contractor uses an MARR of 8%. The crane costs $530,000 and can be sold for $360,000 after 4 years. The cost to operate and maintain the crane is $200,000 per year. Renting the crane costs $330,000 per year including all operating and maintenance costs. Determine the incremental benefit-cost ratio that the contractor should use to decide between buying and renting. Express your answer to two decimal places.

Answer is 1.31

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditors Guide To IT Auditing Software Demo

Authors: Richard E. Cascarino

2nd Edition

1118147618, 978-1118147610

More Books

Students also viewed these Accounting questions

Question

What do brands want to accomplish with mobile media?

Answered: 1 week ago

Question

Describe ERP and how it can create efficiency within a business

Answered: 1 week ago

Question

10. Describe the relationship between communication and power.

Answered: 1 week ago