A cooling load of 12,000 Btu/hr is needed for cryogenic application. To efficiently achieve the low temperature cooling for this application, two refrigeration processes are

A cooling load of 12,000 Btu/hr is needed for cryogenic application. To efficiently achieve the low temperature cooling for this application, two refrigeration processes are connected in cascade configuration, where the heat rejection of the low temperature cycle is the heat input to the high temperature cycle.

If the low temperature cycle has a COP of 3.0. What is the heat rejection of the low temperature cycle?

What is the compressor work for the high temperature cycle, if the high temperature cycles also has a COP of 3.0?

What is the overall COP of the cascade refrigeration system?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles And Modern Applications Of Mass Transfer Operations

Authors: Jaime Benitez

3rd Edition

1119042739, 978-1119042730

More Books

Students also viewed these Chemical Engineering questions

Question

Does it have correct contact information?

Answered: 1 week ago