A Corporation uses a job-order costing system and a predetermined overhead rate based on machine hours. The following information pertains to February of the current
A Corporation uses a job-order costing system and a predetermined overhead rate based on machine hours.
The following information pertains to February of the current year:
Job No. 30 | Job No. 40 | Job No. 50 | Totals | ||||
Work in process, February 1 | $ 30,000.00 | $ 40,000.00 | $ 60,000.00 | $ 130,000.00 | |||
February production activity: | |||||||
Materials requisitioned and used | $ 15,000.00 | $ 20,000.00 | $ 30,000.00 | $ 65,000.00 | |||
Direct labor costs | $ 5,000.00 | $ 10,000.00 | $ 15,000.00 | $ 30,000.00 | |||
Machine hours | $ 1,500.00 | $ 2,000.00 | $ 1,000.00 | $ 4,500.00 |
At the beginning of the year, the company estimated manufacturing overhead for the year would be $500,000 and machine hours used would be 50,000.
Questions:
- Compute the predetermined overhead rate.
- Determine the total cost associated with each job: Job No. 30, Job No. 40 and Job No. 50
- Give the general journal entry to record when Job 40 was completed.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started