A developer is building a Data Centre in Longeuil, Quebec. She has already negociated a lease with one operator, who will take up the entire

A developer is building a Data Centre in Longeuil, Quebec. She has already negociated a lease with one operator, who will take up the entire building. The operator will move in and start paying
rent as soon as construction is finished.
Lease, financing and market data are shown below.
a) Based on the budget, calculate the outstanding construction loan at the end construction.
b) The developer plans to take-out a mortgage at the end of construction, when the lease starts. How much equity will she be able to withdraw?
Please make your calculations to the right of the data on this worksheet.
Upload your file onto Moodle by the deadline indicated on the course outline.
Grade (out of 10):
Construction loan:
Cash flows:
The land is purchased and site preparation will be
paid in the first month. The hard costs will be
evenly distributed over months 2 to 10. The soft
costs (excluding interest) are evenly distributed
over the 10 month period. All cash flows oceur at
the end of the month.
Development Budget:
Lease:
Type
Mortgage loan:
Term (years)
Amortization period (years)
Mortgage rate
MasimumLTVA developer is building a Data Centre in Longeuil, Quebec. She has already negociated a lease with one operator, who will take up the entire building. The operator will move in and start paying rent as soon as construction is finished.
Lease, financing and market data are shown below.
a) Based on the budget, calculate the outstanding construction loan at the end of construction.
b) The developer plans to take-out a mortgage at the end of construction, when the lease starts. How much equity will she be able to withdraw?
Please make your calculations to the right of the data on this worksheet. This is an Excel assignment.
Data:
Construction Loan:
LTC 65%
Interest Rate 6%
Cash Flows:
The land is purchased and site preparation will be paid in the first month. The hard costs will be evenly distributed over months 2 to 10. The soft costs (excluding interest) are evenly distributed over the 10 month period. All cash flows occur at the end of the month.
DEVELOPMENT BUDGET:
Land: 1,250,000
Site Preparation: 25,000
Hard costs: 4,000,000
Permits: 50,000
Property taxes: 100,000
Insurance: 10,000
Professionals: 150,000
---------------
Total for this: 5,585,000
Estimated interest: 60,500
Final Total: 5,645,500
LEASE:
Type: NNN (triple net)
Total Base Rent per year: 400,000
Building Operating Expenses: 75,000
CAP RATE: 5.5%
MORTGAGE LOAN:
Term (years): 5
Ammortization period (years): 20
Mortgage rate: 4.0%
Maximum LTV: 75%
Minimum DSCR: 1.25%
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Behavioural Approaches To Corporate Governance

Authors: Cameron Elliott Gordon

1st Edition

1138611395, 978-1138611399

More Books

Students also viewed these Finance questions

Question

4. Describe three kinds of personality units that are not traits.

Answered: 1 week ago