Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The following is the activity list for a project: Activity Predecessor Normal Crash Normal Crash duration duration cost cost (weeks) (weeks) $12,000 $20,000 $24,000
The following is the activity list for a project: Activity Predecessor Normal Crash Normal Crash duration duration cost cost (weeks) (weeks) $12,000 $20,000 $24,000 $22,000 $20,000 A 2 B A 5. 4 A 3 $16,000 $24,000 $28,000 $24,000 B 4 $20,000 $28,000 B 4 F 7 6 $38,000 $20,000 $30,000 G D. 3 2 $14,000 H E,F 4 3 $18,000 a. Draw an activity on node (AON) diagram to represent the project. b. Apply the critical path method and determine the following using the normal durations of the activities: i. The project duration, ii. The earliest start and finish time of each activity, i. The latest start and finish time of each activity, iv. The slack of each activity, v. The critical path(s). c. Which activity or activities should be crashed and in which sequence to reduce the project duration by 2 weeks? d. What is the resulting total project cost? e. What is (are) the critical path(s) of the project after crashing?
Step by Step Solution
★★★★★
3.46 Rating (156 Votes )
There are 3 Steps involved in it
Step: 1
a Network Diagram Activity on Node D G B End dummy A b Draw the table listing allowable crash time a...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started