Question

1 Approved Answer

(a) Draw the network. (b) Find the ESs, LSs, and slacks. (c) Find the critical path. (d) If the project has a 1 1/2-year deadline

(a) Draw the network. (b) Find the ESs, LSs, and slacks. (c) Find the critical path. (d) If the project has a 1 1/2-year deadline for reopening, should we consider crashing some activities? Explain.

image text in transcribed
Exercise 4: Given the following highway rerouting project, Immediate Activity Time Activity Predecessor (months A: Schedule crew B: Schedule equipment C: Plan new route A JWaNat D: Costs meet budget? B E: Inform public C, B F: Put out signs C, B G: Begin rerouting D. E (a) Draw the network. (b) Find the ESs, LSs, and slacks. (c) Find the critical path. (d) If the project has a 1 1/2-year deadline for reopening, should we consider crashing some activities? Explain. 8 3 4 4 3 6 A C T 12 0 17 3 4 7 7 2 9 " 3 12 Start 12 5 17 End17 . . . 12 B 6 6 Legend for Solution 14 3 17 Barty Early Irish Aclu Critical Path Firish

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Elementary Statistics

Authors: Robert R. Johnson, Patricia J. Kuby

11th Edition

978-053873350, 9781133169321, 538733500, 1133169325, 978-0538733502

Students also viewed these General Management questions