Question
1 Approved Answer
A ) Draw the Network diagram. B ) Calculate ES , LS , EF , LF , using forward pass and backward pass computation. (
A Draw the Network diagram.
B Calculate ESLSEFLF using forward pass and backward pass computation. Clearly show the calculation
C Identify the Critical Path Activity, explain why the path chosen is the Critical path.
D Identify the project completion time.
Activity Preceding Duration Weeks
A
B A
C A
D A
E B
F B
G CF
H D
I H
J GI
K EJ
L K
M K
N LM
O N
P N
Q P