Question

1 Approved Answer

A dummy activity is used in PERT network to describe the Precedence relationship Resource idleness Resource restriction Necessary time delay

A dummy activity is used in PERT network to describe the
Precedence relationship
Resource idleness
Resource restriction
Necessary time delay