A factory has done an analysis of the maintenance department cost showing that there is a fixed element of Shs. 500,000 per month and a
A factory has done an analysis of the maintenance department cost showing that there is a fixed element of Shs. 500,000 per month and a variable element related to machine hours amounting to Shs. 2,250 per machine hour. What is the expected cost for a month when the planned activity level is (i) 1,500 machine hours (ii) 1,800 machine hours?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To calculate the expected cost for a month we need to consider both the fixed element and the variab...Get Instant Access to Expert-Tailored Solutions