A factory has just received an order for 100 units of an end item, which are to be shipped at the start of week
A factory has just received an order for 100 units of an end item, which are to be shipped at the start of week 8. Relevant information of the end item and the components is as follows. Item End item 2 A B Lead Time On Hand (weeks) Inventory 3 3 1 40 30 20 100 Scheduled receipts 56 at week 3 62 at week 4 Order Policy lot for lot lot for lot lot for lot lot for lot Direct Components A(3), B(2) C(1) C(5) Develop the material requirements plan (please print out an empty MRP table to work with), and determine what the "planned order receipts" is for component C at week 3. A factory has just received an order for 100 units of an end item, which are to be shipped at the start of week 8. Relevant information of the end item and the components is as follows. Item End item A B C D Lead Time On Hand (weeks) Inventory 2 60 10 20 100 20 2 3 1 1 Scheduled receipts Order Policy lot for lot lot for lot 46 at week 4 lot for lot lot for lot 57 at week 2 min. of 600 Direct Components A(4), B(2) C(5) D(1) D(3) Develop the material requirements plan (please print out an empty MRP table to work with), and determine how many units of component D are needed in the "planned order release" at week 2. Input should be an exact number.
Step by Step Solution
★★★★★
3.43 Rating (156 Votes )
There are 3 Steps involved in it
Step: 1
Here is an empty MRP table to work with Item Lead Time weeks On Hand Inventory Scheduled receipts Order Policy Direct Components Gross requirements Net requirements Planned receipts Planned order rele...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started