Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A factory operates two eight - hour shifts per day, five days per week. Their design capacity is 2 1 0 units per hour. Last

A factory operates two eight-hour shifts per day, five days per week. Their design capacity is 210 units per hour. Last week they produced 15,000 units. What was their utilization last week?
State answer as a precent rounded to two decimal places

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Project Management Made Simple

Authors: Terry Schmidt

1st Edition

0470411589, 978-0470411582

More Books

Students also viewed these General Management questions

Question

Demonstrate through language that you are grateful to be informed.

Answered: 1 week ago

Question

Always mention the specifi c problem the customer faced.

Answered: 1 week ago