A factory operates two eight-hour shifts per day, five days per week. Their design capacity is 245 units per hour. Last week they produced 15,000

A factory operates two eight-hour shifts per day, five days per week. Their design capacity is 245 units per hour. Last week they produced 15,000 units. What was their utilization last week?

State answer as a precent rounded to two decimal places

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Time Management For Writers

Authors: Katie Forrest

1st Edition

1711795860, 978-1711795867

More Books

Students also viewed these General Management questions

Question

Describe some common hazards in the contemporary workplace

Answered: 1 week ago